EPA v. City of Liberty Hill
Unilateral Administrative Order Without Adjudication
Case summary
On June 24, 2021, EPA Region 6 issued an Administrative Order (AO) under its authority pursuant to Section 309 of the Clean Water Act to the City of Liberty Hill Wastewater Treatment Plant. The AO was issued in response to effluent violations of permit limits. The AO requires the facility to: 1) submit a list of specific actions taken to correct the violations and 2) submit written certification to EPA that the violations have been corrected and the facility is compliant with its permit. The Respondent must respond to EPA Region 6 within thirty (30) days of the effective dated of the AO.
Defendants (1)
- Honorable Liz BraniganNamed in settlement
Facilities (1)
LIBERTY HILL REGIONAL WWTP
8800 F SE OF INT US HWY 29 AND US HWY 183, WILLIAMSON COUNTY, TX, 78703
Registry ID: 110071711336
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
City of Liberty Hill Administrative Orderentered 2021-06-24
Primary law: CWA
Timeline (4 milestones)
- 2021-06-24Final Order Issued
- 2021-06-28Enforcement Action Data Entered
- 2024-12-03NPDES Closed
- 2024-12-03Enforcement Action Closed
Case metadata
- EPA activity ID
- 3602749696
- Case number
- 06-2021-1730
- Lead agency
- EPA
- Branch
- 6ECDW
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2021-1730 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.