06-2019-1703Administrative - FormalFinal Order IssuedFY 2019· Region 06

EPA v. City of Ruidoso Downs WWTP

Unilateral Administrative Order Without Adjudication

Case summary

On August 28, 2018, the New Mexico Environment Department inspected the City of Ruidoso Downs and the Village of Ruidoso's Wastewater Treatment facility for compliance, with the Multi-Sector General Permit on behalf of the Environmental Protection Agency (EPA). The inspection found the facility not authorized to discharge storm water associated with its industrial activities under the permit. EPA issued Administrative Order CWA-06-2019-1703 requiring the City to take corrective actions to come into compliance.

Defendants (1)

  • City of Ruidoso Downs and the Village of RuidosoNamed in complaintNamed in settlement

Facilities (1)

  • CITY OF RUIDOSO DOWNS WWTP

    26675 US 70, RUIDOSO, NM, 88345

    Registry ID: 110070388577

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • City of Ruidoso Downs WWTPentered 2018-12-03

    Primary law: CWA

Timeline (2 milestones)

  • 2018-12-03Final Order Issued
  • 2018-12-11Enforcement Action Data Entered

Case metadata

EPA activity ID
3601696941
Case number
06-2019-1703
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2019-1703 . Bulk data: ICIS-FEC download summary.