Skip to main content
06-2015-3315Administrative - FormalClosedFY 2015· Region 06

EPA v. Enterprise Products Operating (Mont Belvieu Complex)

Final Order With Penalty

Case summary

On April 6, 2015, EPA Region 6 issued a Consent Agreement and Final Order (CAFO) under its authority pursuant to the Clean Air Act to Enterprise Products Operating LLC (Enterprise). The CAFO was issued in response to violations of Section 112(r)(7) of the Clean Air Act and 40 CFR Part 68-Chemical Accident Prevention Provisions at the Mont Belvieu plant. The CAFO requires Enterprise to pay an assessed penalty of $378,215 within 30 days of the effective date of the CAFO. Additionally, Enterprise must complete a Supplemental Environmental Project which is estimated at $22,000 to the purchase of emergency response equipment for the local fire department.

Defendants (1)

  • Enterprise Products Operating, LLCNamed in complaintNamed in settlement

Facilities (4)

  • ENTERPRISE MONT BELVIEU COMPLEX

    10207 FM 1942 RD, MONT BELVIEU, TX, 77521

    Registry ID: 110056961480

  • ENTERPRISE MONT BELVIEU COMPLEX

    10207 FM 1942 RD, MONT BELVIEU, TX, 77521

    Registry ID: 110056961480

  • ENTERPRISE MONT BELVIEU COMPLEX

    10207 FM 1942 RD, MONT BELVIEU, TX, 77521

    Registry ID: 110056961480

  • ENTERPRISE MONT BELVIEU COMPLEX

    10207 FM 1942 RD, MONT BELVIEU, TX, 77521

    Registry ID: 110056961480

Statutes cited

  • CAA 112[R][7]Prevention of Accidental Release/Risk Management Plans (RMPs)

Enforcement conclusions (1)

  • Enterprise Products Operating (Mont Belvieu Complex)entered 2015-04-06

    Primary law: CAA

    Federal penalty: $378,215 · SEP: $22,000

Timeline (5 milestones)

  • 2014-12-09Complaint Filed/Proposed Order
  • 2014-12-22Enforcement Action Data Entered
  • 2015-04-06Final Order Issued
  • 2015-07-15Enforcement Action Closed
  • 2015-07-15Air Resolved

Case metadata

EPA activity ID
3600028753
Case number
06-2015-3315
Lead agency
EPA
Branch
6EN-A
EPA region
06
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/Risk Management Plans (RMPs)