EPA v. Energy Production Company
Unilateral Administrative Order Without Adjudication
Case summary
On December 2, 2014, EPA Region 6 issued an Administrative Order (AO under its authority pursuant to Sections 308 and 309 of the Clean Water Act (CWA) to Energy Production Company (Respondent) located in Mineola, Texas. The AO was issued in response to an unauthorized produced water discharge to a waters of the US. The AO requires the Respondent to (1) Immediately cease all discharges of pollutants from the facility; and, (2) remove all pollutants from the impacted water body and all water bodies down gradient, which was discharged from the facility on or about August 28, 2014. Respondent must respond to EPA Region 6 within 30 days of receiving this AO.
Defendants (1)
- Energy Production CompanyNamed in settlement
Facilities (1)
ENERGY PRODUCTION COMPANY - SCHNEIDER BUDA UNIT LEASE
APPROXIMATELY 1 MILE NORTHEAST OF CR2655 (32.68027, MINEOLA, TX, 75773
Registry ID: 110062646784
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Energy Production Companyentered 2014-12-02
Primary law: CWA
Timeline (4 milestones)
- 2014-12-02Final Order Issued
- 2014-12-16Enforcement Action Data Entered
- 2015-09-16NPDES Closed
- 2015-09-16Enforcement Action Closed
Case metadata
- EPA activity ID
- 3600026400
- Case number
- 06-2015-1706
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit