06-2014-1701Administrative - FormalClosedFY 2014· Region 06

EPA v. Mesa Verde, Inc.

Final Order No Penalty

Case summary

Respondent, Mesa Verde, Inc. owned or operated the Ruidoso concrete batch plant, an industrial site located in Ruidoso, Lincoln County, New Mexico. AO issued on 1/6/2014 for no permit and no SWPPP at the facility. Violations were identified during a July 23, 2013 inspection by NMED on behalf of EPA.

Defendants (1)

  • Mesa Verde, Inc.Named in complaintNamed in settlement

Facilities (1)

  • MESA VERDE INC.

    P.O. BOX 907, ALAMOGORDO, NM, 88311-0907

    Registry ID: 110057191195

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Mesa Verde, Inc.entered 2014-01-06

    Primary law: CWA

Timeline (4 milestones)

  • 2014-01-06Final Order Issued
  • 2014-03-28Enforcement Action Data Entered
  • 2015-06-26NPDES Closed
  • 2015-06-26Enforcement Action Closed

Case metadata

EPA activity ID
3400223795
Case number
06-2014-1701
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations