Skip to main content
06-2012-1846Administrative - FormalClosedFY 2012· Region 06

EPA v. Chaparral Energy LLC

Unilateral Administrative Order Without Adjudication

Case summary

On June 5, 2012, EPA Region 6 issued an Administrative Order (AO) under its authority pursuant to Sections 308 and 309 of the Clean Water Act (CWA) to Chaparral Energy, LLC located in Osage County, Oklahoma. The AO was issued in response to a violation of Section 301 of the CWA. The AO requires Chaparral Energy LLC to: 1) Cease all discharges of pollutants from the facility; 2) remove all brine from the flow path located in between the facility and Hay Creek; and 3) remove all brine from Hay Creek. Chaparral Energy, LLC must respond to EPA Region 6 within 30 days of recieving the AO.

Defendants (1)

  • Chaparral Energy LLCNamed in settlement

Facilities (1)

  • NW-19-27-06

    NW/4, SEC. 19, T 27N, R 06E, PAWHUSKA, OK, 74056

    Registry ID: 110040428016

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Chaparral Energy LLCentered 2012-06-05

    Primary law: CWA

Timeline (3 milestones)

  • 2012-06-05Final Order Issued
  • 2012-06-14Enforcement Action Data Entered
  • 2015-09-16Enforcement Action Closed

Case metadata

EPA activity ID
3000029140
Case number
06-2012-1846
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2012-1846 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.