EPA v. Bandwheel Production Co., LLC
Unilateral Administrative Order Without Adjudication
Case summary
On March 23, 2012, EPA Region 6 issued an Administrative Order (AO) under its authority pursuant to Section 308 and 309(a) of the Clean Water Act (CWA) to Bandwheel Production Co., LLC, located in Osage County, Oklahoma. The AO was issued in response to violations of Section 301 of the CWA. The AO requires Bandwheel Production Co., LLC to (1) cease discharges of pollutants from the facility; (2) remove all brine from the flow path located in between the facility and the tributary of Hominy Creek; (3) remove brine from the tributary of Hominy Creek; and (4) submit written certification. Bandwheel Production Co., LLC must respond to EPA Region 6 within thirty (30) days of receiving the AO.
Defendants (1)
- Bandwheel Production Co., LLCNamed in settlement
Facilities (1)
NE-13-23-8
NE/4, SEC. 13, T 23N, R 8E, HOMINY, OK, 74035
Registry ID: 110030904662
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Bandwheel Production Co., LLCentered 2012-03-23
Primary law: CWA
Timeline (3 milestones)
- 2012-03-23Final Order Issued
- 2012-03-30Enforcement Action Data Entered
- 2013-06-26Enforcement Action Closed
Case metadata
- EPA activity ID
- 3000008567
- Case number
- 06-2012-1819
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2012-1819 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.