Skip to main content
06-2012-1804Administrative - FormalClosedFY 2012· Region 06

EPA v. William J. Frisby

Unilateral Administrative Order Without Adjudication

Case summary

On February 23, 2012, EPA Region 6 issued an Administrative Order (AO) under its authority pursuant to Section 309 of the Clean Water Act (CWA) to William J. Frisby located in Union Co., Arkansas. The AO was issued in response to violations of Section 301 of the CWA. The AO requires William J. Frisby to (1) cease all discharges of pollutants from the facility; (2) remove all brine and contaminated soils from the area between the facility and N. Lapile Creek. William J. Frisby must respond to EPA Region 6 within 30 days if the AO.

Defendants (1)

  • William J. FrisbyNamed in settlement

Facilities (1)

  • NW-31-17-13

    NORTHWEST QUARTER SEC. 31, T 17 S, R 13 W, EL DORADO, AR, 71730

    Registry ID: 110045461497

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • William J. Frisbyentered 2012-02-23

    Primary law: CWA

Timeline (3 milestones)

  • 2012-02-23Final Order Issued
  • 2012-03-14Enforcement Action Data Entered
  • 2015-09-16Enforcement Action Closed

Case metadata

EPA activity ID
3000004075
Case number
06-2012-1804
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2012-1804 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.