EPA v. Beren Corporation
Unilateral Administrative Order Without Adjudication
Case summary
Violation: The Respondent's tank battery facility was a point source which discharged a pollutant to a waters of the US. The facility was inspected by the EPA on February 15, 2011, and during the inspection the EPA observed where the facility had discharged oil field brine to a tributary of Mill Creek. Relief: An Administrative Order was issued on March 7, 2011 requiring the following: cease all discharges of pollutants from the facility; remove all the brine and contaminated soils from the flow path; remove brine from Mill Creek; and, submit written certfication that these requirements have been completed.
Defendants (1)
- Beren CorporationNamed in settlement
Facilities (1)
SW-11-17-14
SW/4, SEC. 11, T 17S, R 14W, SMACKOVER, AR, 71762
Registry ID: 110043467717
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Beren Corporationentered 2011-03-07
Primary law: CWA
Timeline (3 milestones)
- 2011-03-07Final Order Issued
- 2011-03-22Enforcement Action Data Entered
- 2012-03-27Enforcement Action Closed
Case metadata
- EPA activity ID
- 2600005966
- Case number
- 06-2011-1783
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2011-1783 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.