06-2011-1782Administrative - FormalClosedFY 2011· Region 06

EPA v. Beren Corporation

Unilateral Administrative Order Without Adjudication

Case summary

Violation: The Respondent's tank battery facility was a point source which discharged a pollutant to a waters of the US. The facility was inspected by the EPA on February 15, 2011, and during the inspection the EPA observed where the facility had discharged oil field brine and wastewater to Mill Creek. Relief: An Administrative Order was issued on March 7, 2011 requiring the following: cease all discharges of pollutants from the facility; remove all the brine and contaminated soils from the flow path; remove brine from Mill Creek; and, submit written certification that these reqirements have ben completed.

Defendants (1)

  • Beren CorporationNamed in settlement

Facilities (1)

  • SE-11-17-14

    SE/4, SEC. 11, T 17S, R 14W, SMACKOVER, AR, 71762

    Registry ID: 110043467708

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Beren Corporationentered 2011-03-07

    Primary law: CWA

Timeline (3 milestones)

  • 2011-03-07Final Order Issued
  • 2011-03-22Enforcement Action Data Entered
  • 2012-03-27Enforcement Action Closed

Case metadata

EPA activity ID
2600005982
Case number
06-2011-1782
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit