EPA v. Oakland Petroleum Operating, Inc.
Unilateral Administrative Order Without Adjudication
Case summary
Violation: The Respondent's tank battery facility was a point source which discharged a pollutant to a waters of the US. The facility was inspected by the EPA on September 21, 2010, and at the time of the inspection the EPA observed that the facility had discharged oil field brine to Turkey Creek. Relief: An Administrative Order for compliance is being issued requiring the Respondent to perform the following: stop the discharge; remove the brine from the flow path located in-between the facility and Turkey Creek; remove the brine from Turkey Creek; and, submit written certification that these activities have been performed.
Defendants (1)
- Oakland Petroleum Operating, Inc.Named in settlement
Facilities (1)
NE-30-29-11
NE/4, SEC. 30, T 29, R 11, BARNSDALL, OK, 74002
Registry ID: 110028170422
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Oakland Petroleum Operating, Inc.entered 2010-09-24
Primary law: CWA
Timeline (3 milestones)
- 2010-09-24Final Order Issued
- 2010-10-06Enforcement Action Data Entered
- 2011-08-02Enforcement Action Closed
Case metadata
- EPA activity ID
- 2200018406
- Case number
- 06-2010-1927
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2010-1927 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.