EPA v. Petro General, Inc.
Unilateral Administrative Order Without Adjudication
Case summary
Violation: The Respondent's tank battery facility was a point source which discharged a pollutant to a waters of the US. The facility was inspected by the EPA on August 31, 2010. During the inspection the EPA inspector observed where the facility had discharged oil field brine to a tributary of Rock Creek. Relief: A cease and desist AO is being issued to the Respondent requiring the following: cease the discharges of pollutants from the facility; remove all the brine from the flow path; remove all the brine from the impacted water body; and to submit written certification.
Defendants (1)
- Petro General, Inc.Named in settlement
Facilities (1)
SE-09-21-12
SOUTHEAST QUARTER OF SEC. 09, T 21N, R 12E, SPERRY, OK, 74073
Registry ID: 110042335979
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Petro General, Inc.entered 2010-09-03
Primary law: CWA
Timeline (3 milestones)
- 2010-09-03Final Order Issued
- 2010-09-03Enforcement Action Data Entered
- 2011-08-02Enforcement Action Closed
Case metadata
- EPA activity ID
- 2200004959
- Case number
- 06-2010-1922
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2010-1922 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.