EPA v. Lone Mountain Contracting, Inc (NMU001668)
Final Order With Penalty
Case summary
A stormwater compliance inspection was conducted July 13, 2010, by the New Mexico Environment Department, at the construction site of Alexander Gusdorf Eco-Park in the Town of Taos, NM, to determine compliance with the Stormwater Construction General Permit. It was determined that Lone Mountain Contracting, Inc, had failed to submit a Notice of Intent for permit coverage and did not have a Stormwater Pollution Prevention Plan. An Expedited Settlement Offer was extended to quickly settle the issues and collect a penalty for the violations.
Defendants (1)
- Lone Mounain Contracting, Inc (NMU001668)Named in complaintNamed in settlement
Facilities (1)
TOWN OF TAOS ALEXANDER GUSDORF ECO-PARK
1400 CAMINO DE LA PLACITA, TAOS, NM, 87571
Registry ID: 110042347537
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Lone Mountain contracting, Inc (NMU001668)entered 2011-06-01
Primary law: CWA
Federal penalty: $3,000
Timeline (5 milestones)
- 2010-08-06Enforcement Action Data Entered
- 2010-11-26Complaint Filed/Proposed Order
- 2011-06-01Final Order Issued
- 2011-06-22NPDES Closed
- 2011-06-22Enforcement Action Closed
Case metadata
- EPA activity ID
- 1800119195
- Case number
- 06-2010-1907
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2010-1907 . Bulk data: ICIS-FEC download summary.