EPA v. Ash Grove Cement Company (National Case)
Final Order With Penalty
Case summary
The consent decree was lodged on June 19, 2013. Ash Grove has agreed to pay to the United States as a civil penalty the sum of $1,666,000 together with interest accruing from the Effective Date through the date of payment. The consent decree requires Ash Grove to install and continuously operate current best available control technology (BACT) and meet NOx emission limits. Ash Grove is also required to meet unit specific BACT level SO2 emission limits for all kilns. In Region 6, Ash Grove will install SNCR technology at Foreman Kiln 4 and will retire Midlothian Kiln 1 and Midlothian Kiln 2. Ash Grove agreed not to operate Midlothian Kiln 3 unless and until Midlothian Kiln 3 has been Reconstructed. The, Plaintiff, the United States of America, on behalf of the United States Environmental Protection Agency (herein U.S. EPA) has, simultaneously with the lodging of this Consent Decree, filed a Complaint against Defendant Ash Grove Cement Company (Defendant), pursuant to Sections 113(b) and 167 of the Clean Air Act (Clean Air Act or Act), 42 U.S.C. 7413(b) and 7477, for injunctive relief and the assessment of civil penalties for violations of one or more of the following statutory and regulatory requirements of the Act at one or more of each of Defendant?s Portland cement plants which collectively are located in nine (9) different states within the United States: the Prevention of Significant Deterioration (PSD) provisions of the Act, 42 U.S.C. 7470-7492; and/or the nonattainment New Source Review (nonattainment NSR) provisions of the Act, 42 U.S.C. 7501-7515; the New Source Performance Standards (NSPS) provisions of the Act, 42 U.S.C. 7411; the federally-approved and enforceable state implementation plans (SIPs), which incorporate and/or implement the above-listed federal PSD and/or nonattainment NSR requirements and NSPS Requirements; Title V of the Act, 42 U.S.C. 7661-7661f; and Title Vs implementing federal and state regulations.
Defendants (2)
- Ash Grove Texas, L.P.
- Ash Grove Cement CompanyNamed in complaintNamed in settlement
Facilities (2)
ASH GROVE CEMENT COMPANY
4343 HIGHWAY 108, FOREMAN, AR, 71836
Registry ID: 110000597729
ASH GROVE CEMENT
900 GIFCO RD, MIDLOTHIAN, TX, 76065
Registry ID: 110000459192
Statutes cited
- CAA 110 — Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
- CAA 111 — New Source Performance Standards
- CAA 502 — Operating Permits (Title V)
- CAA 165 — Prevention of Significant Deterioration (PSD)
Enforcement conclusions (1)
Ash Grove Cement Company (National Case)entered 2013-08-14
Primary law: CAA
Federal penalty: $416,500 · State/local: $103,000
Timeline (8 milestones)
- 2009-09-15Referred To Dept Of Justice
- 2009-09-28Enforcement Action Data Entered
- 2012-10-18Supplemental Referral-Adding parties, counts
- 2013-06-19Final Order Lodged
- 2013-06-19Complaint Filed With Court
- 2013-08-14Final Order Entered
- 2018-05-01Air Resolved
- 2019-02-19Enforcement Action Closed
Case metadata
- EPA activity ID
- 1800027297
- Case number
- 06-2009-3401
- DOJ docket
- 90-5-2-1-09875
- Lead agency
- EPA
- Branch
- 6EN-A
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- Implementation Plan for National Primary and Secondary Ambient Air Quality Standards
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2009-3401 . Bulk data: ICIS-FEC download summary.