EPA v. Linn Energy, LLC
Unilateral Administrative Order Without Adjudication
Case summary
Violation: The Respondent's oil field facility was a point source discharge of a pollutant to a waters of the US. The facility was inspected by the EPA on June 4, 2009, the inspector observed where oil field brine had been discharged from a manfold to a tributary of Hominy Creek and to Hominy Creek. Fluids located in the tributary of Hominy Creek measured 16,500 parts-per-million total soluble salts. Relief: An Administrative Order is being issued to the Respondent requirng them to: cease all discharges of polltants from the facility; remove all brine from the flow path located between the facility and Hominy Creek; and submit written certification within 30 days.
Defendants (1)
- Linn Energy, LLCNamed in settlement
Facilities (1)
NE-21-24-07
NE/4, SEC. 21, T 24N, R 7E, HOMINY, OK, 74035
Registry ID: 110039154553
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Linn Energy, LLCentered 2009-06-12
Primary law: CWA
Timeline (3 milestones)
- 2009-06-12Final Order Issued
- 2009-07-20Enforcement Action Data Entered
- 2011-08-02Enforcement Action Closed
Case metadata
- EPA activity ID
- 1800007791
- Case number
- 06-2009-1856
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2009-1856 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.