EPA v. Petco Petroleum Corporatin
Unilateral Administrative Order Without Adjudication
Case summary
Violation: Respondent's oil field facility was a point source discharge of a pollutant to a waters of the US. The violation was identified based on an EPA inspection conducted on March 26, 2009 at a facility located in the Northeast Quarter Section of Section 4, Township 18 North, Range 7 East, Creek Co., Oklahoma. The violation found consists of an unauthorized discharge of oil field brine to a tributary of the Cimmaron River. Relief: A Cease and Desist Administrative Order is being issued to the Respondent requiring the following: cease all discharges of pollutants from the facility; remove all the brine located in-between the facility and the point of entry; remove all the brine from the point of entry; and to submit written certification.
Defendants (1)
- Petco Petroleum CorporationNamed in settlement
Facilities (1)
NE-04-18-07
NE/4, SEC. 04, T 18N, R 07E, CUSHING, OK, 74023
Registry ID: 110014416943
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
Petco Petroleum Corporationentered 2009-03-31
Primary law: CWA
Timeline (3 milestones)
- 2009-03-31Final Order Issued
- 2009-04-02Enforcement Action Data Entered
- 2011-08-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 1400037278
- Case number
- 06-2009-1805
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2009-1805 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.