06-2009-1794Administrative - FormalClosedFY 2009· Region 06

EPA v. Johnson & Ernst Operating Co.

Unilateral Administrative Order Without Adjudication

Case summary

Violation: The Respondent's tank battery facility was a point source discharge of a pollutant to waters of the US. The facility was inspected by an EPA inspector on February 10, 2009, which the inspector observed the facility had discharged brine to a tributary of Beaver Creek. Relief: An Administrative Order is being issued to the Respondent requiring the following: cease all discharges of pollutants from the facility; remove all the brine in-between the facility and the point of entry; remove all the brine from the impacted water body; and submit written certification.

Defendants (1)

  • Johnson & Ernst Operating Co.Named in settlement

Facilities (1)

  • WAGGONER CS LEASE - RRC 06672

    N33° 58.620', W99° 8.126', VERNON, TX, 76384

    Registry ID: 110038397400

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Johnson & Ernst Operating Co.entered 2009-02-12

    Primary law: CWA

Timeline (3 milestones)

  • 2009-02-12Final Order Issued
  • 2009-03-25Enforcement Action Data Entered
  • 2011-08-01Enforcement Action Closed

Case metadata

EPA activity ID
1400035645
Case number
06-2009-1794
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2009-1794 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.