Skip to main content
06-2007-1853Administrative - FormalClosedFY 2007· Region 06

EPA v. Wellco Energy, Inc.

Unilateral Administrative Order Without Adjudication

Case summary

VIOLATIONS: The Respondent's oil field facility was a point source discharge of pollutants, specifically produced water, to the receiving waters of a tributary of Clem Creek, located in the Northeast Quarter of Section 7, Township 23 North, Range 11 East, Osage County, Oklahoma. An April 5, 2007, EPA inspection documented the discharge of brine from the facility. RELIEF: The Order specifies that the Respondent shall take the necessary steps to prevent future discharges by neutralizing or removing contaminated soils. The Order also recommends for the Respondent to reconstruct the secondary containment around the facility, and to install a sump pump in the lowest most area inside the secondary containment.

Defendants (1)

  • Wellco Energy, Inc.Named in settlement

Facilities (1)

  • NE-07-23-11

    NE/4, SEC. 07, T 23N, R 11E, BARNSDALL, OK, 74002

    Registry ID: 110030902511

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Wellco Energy, Inc.entered 2007-05-22

    Primary law: CWA

Timeline (3 milestones)

  • 2007-04-26Enforcement Action Data Entered
  • 2007-05-22Final Order Issued
  • 2009-07-29Enforcement Action Closed

Case metadata

EPA activity ID
600040391
Case number
06-2007-1853
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2007-1853 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.