06-2007-1778Administrative - FormalClosedFY 2007· Region 06

EPA v. Burnett Construction

Unilateral Administrative Order Without Adjudication

Case summary

Violations: 1. Failure to have the SWPPP at the construction site. 2. SWPPP was not available upon request for the EPA and ADEQ inspectors. 3. No controls measures installed at the construction site.

Defendants (1)

  • Burnett ConstructionNamed in settlement

Facilities (1)

  • BURNETT HIGHWAY 72

    HIGHWAY 72, BENTONVILLE, AR, 72712

    Registry ID: 110025345570

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Burnett Constructionentered 2007-03-16

    Primary law: CWA

Timeline (3 milestones)

  • 2007-02-07Enforcement Action Data Entered
  • 2007-03-16Final Order Issued
  • 2007-08-03Enforcement Action Closed

Case metadata

EPA activity ID
600027698
Case number
06-2007-1778
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations