Skip to main content
06-2007-1776Administrative - FormalClosedFY 2007· Region 06

EPA v. Dixie Construction LLC

Unilateral Administrative Order Without Adjudication

Case summary

Violations: 1. Failure to post the Storm Water Construction General Permit certification, a copy of the Notice of intent confirmation letter, and a brief description of the project, along with the permit number at the construction site. 2. Failure to develop an adequate Storm Water Pollution Prevention Plan for the construction site. 3. Failure to perform required inspections of the construction site.

Defendants (1)

  • Dixie Construction LLCNamed in settlement

Facilities (1)

  • ELM SPRINGS BUSINESS PARK

    4231 ELM SPRINGS ROAD, SPRINGDALE, AR, 72764

    Registry ID: 110025048678

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Dixie Construction LLCentered 2007-03-14

    Primary law: CWA

Timeline (3 milestones)

  • 2007-02-26Enforcement Action Data Entered
  • 2007-03-14Final Order Issued
  • 2009-07-01Enforcement Action Closed

Case metadata

EPA activity ID
600029398
Case number
06-2007-1776
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2007-1776 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.