EPA v. BDSP, Inc.
Unilateral Administrative Order Without Adjudication
Case summary
VIOLATIONS: The Respondentýs oil field facility was a point source discharge of pollutants, specifically produced water, to the receiving waters of a tributary of Walnut Creek, located in the Southeast Quarter of Section 23, Township 4 South, Range 3 West, Carter County, Oklahoma. A March 8, 2006 EPA inspection documented the discharge of brine from the facility. RELIEF: The Order specifies that the Respondent should also take steps to cease all discharges of pollutants; take the necessary steps to prevent future discharges; and to submit a facility work plan describing the specific corrective actions which will correct the violations.
Defendants (1)
- BDSP, Inc.Named in settlement
Facilities (1)
SE-23-04-03
SE/4, SEC. 23, T 04S, R 03W, ARDMORE, OK, 73401
Registry ID: 110015773359
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
BDSP, Inc.entered 2006-06-12
Primary law: CWA
Timeline (3 milestones)
- 2006-04-27Enforcement Action Data Entered
- 2006-06-12Final Order Issued
- 2012-03-27Enforcement Action Closed
Case metadata
- EPA activity ID
- 176063
- Case number
- 06-2006-2041
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit