Skip to main content
06-2006-2009Administrative - FormalClosedFY 2006· Region 06

EPA v. XTO Energy, Inc.

Unilateral Administrative Order Without Adjudication

Case summary

VIOLATIONS: The Respondent's drilling mud land farming operation was a point source discharge of pollutants, specifically drilling mud, to the receiving waters of a tributary of the Brazos River, located in Johnson County, Texas. A March 14, 2006, EPA inspection observed drilling mud was discharged from the Respondent�s facility. RELIEF: The Order specifies that the Respondent should take steps to cease all discharges of pollutants and to take the necessary steps to prevent future discharges. Also, requires the Respondent to submit information to the EPA in regards to the spill.

Defendants (1)

  • XTO Energy, Inc.Named in settlement

Facilities (1)

  • XTO ENERGY - MUD FARMING OPERATION - JOHNSON CO., TX

    810 HOUSTON STREET, FORT WORTH, TX, 76102

    Registry ID: 110024534431

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • XTO Energy, Inc.entered 2006-05-31

    Primary law: CWA

Timeline (3 milestones)

  • 2006-04-18Enforcement Action Data Entered
  • 2006-05-31Final Order Issued
  • 2009-07-01Enforcement Action Closed

Case metadata

EPA activity ID
174823
Case number
06-2006-2009
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2006-2009 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.