EPA v. Eldorado Estates, Phase IV
Unilateral Administrative Order Without Adjudication
Case summary
04/12/05 EPA inspected the Eldorado Estates, Phase IV construction project located at 3100 Deer Run Drive, Little Elm, TX and found the facility non compliant with NPDES storm water regulatory requirements. 02/10/06, EPA issued Administrative Order Docket Number CWA-06-2006-1806 that ordered compliance wit the CWA within 30 days. Respondent submitted information that indicated the violations were addressed under Administrative Order Docket Number CWA-06-2006-1820 and a response submitted to EPA. Review of the information resulted in rescinding the Order CWA-06-2006-1806 with Order CWA-06-2006-1820 remaining active and enforceable.
Defendants (1)
- Highland HomesNamed in complaintNamed in settlement
Facilities (1)
ELDORADO ESTATES, PHASE IV (TXR15J422)
3100 DEER RUN DRIVE, LITTLE ELM, TX, 75068
Registry ID: 110022545995
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Eldorado Estates, Phase IVentered 2006-02-10
Primary law: CWA
Timeline (3 milestones)
- 2006-02-10Final Order Issued
- 2006-02-27Enforcement Action Data Entered
- 2007-03-14Enforcement Action Closed
Case metadata
- EPA activity ID
- 170046
- Case number
- 06-2006-1808
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations