EPA v. El Paso Electric Company (NM0000108)
Unilateral Administrative Order Without Adjudication
Case summary
Respondent has an NPDES discharge permit and violated the permit by failing to reapply for permit coverage at least 180 days in advance of the permit expiration. EPA is Ordering Respondent to complete the application process.
Defendants (1)
- El Paso Electric Company (NM0000108)Named in complaintNamed in settlement
Facilities (4)
EL PASO ELECTRIC CO
3501 DONIPHAN DRIVE, SUNLAND PARK, NM, 88063
Registry ID: 110001547238
EL PASO ELECTRIC CO
3501 DONIPHAN DRIVE, SUNLAND PARK, NM, 88063
Registry ID: 110001547238
EL PASO ELECTRIC CO
3501 DONIPHAN DRIVE, SUNLAND PARK, NM, 88063
Registry ID: 110001547238
EL PASO ELECTRIC CO
3501 DONIPHAN DRIVE, SUNLAND PARK, NM, 88063
Registry ID: 110001547238
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
El Paso Electric Company (NM0000108)entered 2006-05-24
Primary law: CWA
Timeline (4 milestones)
- 2006-03-09Enforcement Action Data Entered
- 2006-05-24Final Order Issued
- 2009-07-01Enforcement Action Closed
- 2009-07-01NPDES Closed
Case metadata
- EPA activity ID
- 170995
- Case number
- 06-2006-1728
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations