EPA v. Aspenwood Development, Inc. (TXU010746)
Unilateral Administrative Order Without Adjudication
Case summary
ASPENWOOD DEVELOPMENT, INC. (TXU010746): A storm water compliance inspection was conducted on June 2, 2005, by EPA at a residential construction site in Arlington, TX. The common plan of development was less than five acres with an total of seven remaining lots to be built out. The Respondent had applied for permit coverage (had not received his confirmation from TCEQ at the time of the inspection), but had not developed a Storm Water Pollution Prevention Plan (SWP3) specific to residential construction. The SWP3 the Respondent was using was the one used by the previous owners and had not been revised to reflect current operations. Because the Respondent met the criteria for the Expedited Settlement Offer, one was extended along with an administrative order for compliance.
Defendants (1)
- Aspenwood Development, Inc. (TXU010746)Named in complaintNamed in settlement
Facilities (1)
ASPENWOOD DEVELOPMENT (TXU010746)
2100 - 2200 LINDBLAD COURT, ARLINGTON, TX, 76013
Registry ID: 110022864239
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Aspenwood Development, Inc. (TXU010746)entered 2005-09-01
Primary law: CWA
Timeline (3 milestones)
- 2005-08-12Enforcement Action Data Entered
- 2005-09-01Final Order Issued
- 2009-07-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 154177
- Case number
- 06-2005-2117
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2005-2117 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.