EPA v. Summer Hill Development (TXR15M322)
Unilateral Administrative Order Without Adjudication
Case summary
SUMMER HILL DEVELOPMENT (TXR15M322): At the request of the City of Ennis, a storm water compliance inspection was conducted by EPA on July 13, 2005, at the construction site of the Walkers Run residential development. During the inspection, it was noted that, among other things, storm water controls had not been properly maintained, or in some cases, installed, and there was litter and debris scattered around the site and in the streets. Because the Respondent met the criteria for the Expedited Settlement Offer, which was drafted and routed for signature.
Defendants (1)
- Summer Hill Development (TXR15M322)Named in complaintNamed in settlement
Facilities (1)
SUMMER HILL DEVELOPMENT (TXR15M322)
309 E. OVILLA RD., SUITE 2100, ENNIS, TX, 75154
Registry ID: 110022870749
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Summer Hill Development (TXR15M322)entered 2005-08-25
Primary law: CWA
Timeline (3 milestones)
- 2005-07-18Enforcement Action Data Entered
- 2005-08-25Final Order Issued
- 2006-03-09Enforcement Action Closed
Case metadata
- EPA activity ID
- 152286
- Case number
- 06-2005-2070
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2005-2070 . Bulk data: ICIS-FEC download summary.