06-2005-2043Administrative - FormalClosedFY 2005· Region 06

EPA v. Robinson Oil Company

Unilateral Administrative Order Without Adjudication

Case summary

Robinson Oil Company CWA-06-2005-2043 OKU000571 VIOLATIONS: The Respondent's oil production facility was a point source of discharge of pollutants, to the receiving waters of Fourmile Creek, located in the Northwest Quarter of Section 25, Township 24 North, Range 9 East, Osage County, Oklahoma. The discharge of oil field brine was documented during a June 3, 2005, inspection. RELIEF: The Order specifies that the Respondent should cease all discharges of pollutants, take corrective actions to prevent deficiencies, remove and properly dispose of fluids, and perform remediation and restoration to impacted soils. It also recommends that the Respondent reconstruct the secondary containment, and install an automatically operated sump pump. Matt Rudolph 5-6434

Defendants (1)

  • Robinson Oil CompanyNamed in complaintNamed in settlement

Facilities (1)

  • NW-25-24-09

    NW/4, SEC. 25, T 24, R 09, WYNONA, OK, 74084

    Registry ID: 110022865531

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Robinson Oil Companyentered 2005-08-09

    Primary law: CWA

Timeline (3 milestones)

  • 2005-06-15Enforcement Action Data Entered
  • 2005-08-09Final Order Issued
  • 2009-07-01Enforcement Action Closed

Case metadata

EPA activity ID
149110
Case number
06-2005-2043
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit