Skip to main content
06-2005-1894Administrative - FormalClosedFY 2005· Region 06

EPA v. Cambro Construction, Inc. (NMU001460)

Unilateral Administrative Order Without Adjudication

Case summary

CAMBRO CONSTRUCTION, INC. (NMU001460): a storm water compliance inspection was conducted November 3, 2004, at the construction site of the Pic Quik Store in Las Cruces, NM. Cambro Construction, Inc., was an operator having day-to-day control of those activities which were necessary to ensure compliance with a Storm Water Pollution Prevention Plan (SWP3) for the site. It was determined that Cambro Construction had not prepared a SWP3, nor applied for permit coverage under the Storm Water Construction General Permit. Cambro Construction was eligible for the Expedited Settlement Offer and that package was prepared and routed for signature.

Defendants (1)

  • Cambro Construction, Inc. (NMU001460) (SB)Named in complaintNamed in settlement

Facilities (1)

  • PIC QUIK STORE

    3811 E. LOHMAN, LAS CRUCES, NM, 88011

    Registry ID: 110020499450

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Cambro Construction, Inc. (NMU001460)entered 2005-05-18

    Primary law: CWA

Timeline (3 milestones)

  • 2005-04-25Enforcement Action Data Entered
  • 2005-05-18Final Order Issued
  • 2005-09-13Enforcement Action Closed

Case metadata

EPA activity ID
146128
Case number
06-2005-1894
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations