EPA v. Alice Isaac Tank Battery
Final Order With Penalty
Case summary
Summary of Findings * Inspections and tests required by 40 CFR Part 112 are not in accordance with written procedures developed for the facility. * No training on the operation and maintenance of equipment to prevent discharges. * Excessive vegetation which affects the integrity an/or walls of containment system are slightly eroded or have low areas. * Visual inspections of containers, foundation and supports are not conducted periodically for deterioration and maintenance needs. * Above ground valves and pipelines are nto examined periodically ona scheduled basis for general condition (includes items, such as: flange joints, valve glands 2nd bodies, drip pans, pipeline supports, bleeder and gauge valves, polish rods/stuffing box. * Brine and saltwater disposal facilities are not examined often.
Defendants (1)
- Alice Isaac Tank BatteryNamed in complaintNamed in settlement
Facilities (1)
ALICE ISAAC TANK BATTERY
NW/4NE/4 SEC. 19, T-2S, R-7W, RATLIFF CITY, OK, 73481
Registry ID: 110018926340
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
Alice Isaac Tank Batteryentered 2004-08-03
Primary law: CWA
Federal penalty: $1,200
Timeline (4 milestones)
- 2004-07-23Enforcement Action Data Entered
- 2004-08-03Enforcement Action Closed
- 2004-08-03Complaint Filed/Proposed Order
- 2004-08-03Final Order Issued
Case metadata
- EPA activity ID
- 124017
- Case number
- 06-2004-4387
- Lead agency
- EPA
- Branch
- 6SF-R
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2004-4387 . Bulk data: ICIS-FEC download summary.