EPA v. S&B Construction, Inc and Associates (SB)
Unilateral Administrative Order Without Adjudication
Case summary
Unauthorized land clearing and discharge of fill material onto 7 acres of forested wetlands adjacent to Mud Creek. The creek and adjacent wetlands are tributary to the Red River watershed. The site is located in Idabel, OK
Defendants (1)
- S&B Construction, Inc and AssociatesNamed in complaintNamed in settlement
Facilities (1)
S&B CONSTRUCTION, INC AND ASSOCIATES (SB)
PO BOX 1683, MCALESTER, OK, 74502
Registry ID: 110018914772
Statutes cited
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
S&B Construction, Inc and Associatesentered 2004-09-30
Primary law: CWA
Timeline (4 milestones)
- 2004-09-30Complaint Filed/Proposed Order
- 2004-09-30Final Order Issued
- 2004-09-30Enforcement Action Data Entered
- 2005-07-26Enforcement Action Closed
Case metadata
- EPA activity ID
- 129711
- Case number
- 06-2004-2712
- Lead agency
- EPA
- Branch
- 6WQ-E
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- Permits for Dredge and Fill Material