06-2004-2712Administrative - FormalClosedFY 2004· Region 06

EPA v. S&B Construction, Inc and Associates (SB)

Unilateral Administrative Order Without Adjudication

Case summary

Unauthorized land clearing and discharge of fill material onto 7 acres of forested wetlands adjacent to Mud Creek. The creek and adjacent wetlands are tributary to the Red River watershed. The site is located in Idabel, OK

Defendants (1)

  • S&B Construction, Inc and AssociatesNamed in complaintNamed in settlement

Facilities (1)

  • S&B CONSTRUCTION, INC AND ASSOCIATES (SB)

    PO BOX 1683, MCALESTER, OK, 74502

    Registry ID: 110018914772

Statutes cited

  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • S&B Construction, Inc and Associatesentered 2004-09-30

    Primary law: CWA

Timeline (4 milestones)

  • 2004-09-30Complaint Filed/Proposed Order
  • 2004-09-30Final Order Issued
  • 2004-09-30Enforcement Action Data Entered
  • 2005-07-26Enforcement Action Closed

Case metadata

EPA activity ID
129711
Case number
06-2004-2712
Lead agency
EPA
Branch
6WQ-E
EPA region
06
Voluntary self-disclosure
No
Primary statute
Permits for Dredge and Fill Material

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2004-2712 . Bulk data: ICIS-FEC download summary.