Skip to main content
06-2004-2165Administrative - FormalClosedFY 2004· Region 06

EPA v. Eagle Contracting, LP (TXR10QR54)

Unilateral Administrative Order Without Adjudication

Case summary

EAGLE CONTRACTING, LP (TXR10QR54): A storm water compliance inspection was conducted on September 9, 2003, at the construction site of the City of Plainview wastewater treatment plant. At commencement of activities at the site, the City was exempt by from the requirement of applying for construction permit coverage under Phase I regulations. Although the site was less than five acres, Eagle Contracting, LP, applied for permit coverage under the EPA 1998 Construction General Permit. The March 5, 2003, TCEQ Construction General Permit granted automatic coverage for small sites if a construction site notice was signed and posted and a Storm Water Pollution Prevention Plan (SWPPP) was developed. Eagle Contracting, LP, did not post the required notice, effectively rendering the company without permit coverage for at least six months. They had also failed to install the necessary controls to minimize pollutants from being discharged from the site. Eagle Contracting, LP, failed to establish final stabilization prior to leaving the site. An administrative order was drafted to address these violations. Contact: Diana McDonald (6EN-WC), (214) 665-7495

Defendants (1)

  • Eagle Contracting, LP (TXR10QR54)Named in complaintNamed in settlement

Facilities (1)

  • EAGLE CONTRACTING, LP / PLAINVIEW, TX WWTP (TXR10QR54)

    607 SOUTH PEARSON, KELLER, TX, 76248

    Registry ID: 110016669121

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Eagle Contracting, LP (TXR10QR54)entered 2004-04-30

    Primary law: CWA

Timeline (3 milestones)

  • 2004-04-16Enforcement Action Data Entered
  • 2004-04-30Final Order Issued
  • 2009-07-01Enforcement Action Closed

Case metadata

EPA activity ID
117886
Case number
06-2004-2165
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2004-2165 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.