JULIAN P. BARRY GENERAL CONTRACTOR, LP (NMU001409): A storm water compliance inspection was conducted by the New Mexico Environment Department on March 24, 2004, to evaluate the compliance of Julian P. Barry General Contractor, LP, with the EPA Construction General Permit at the construction site of Old Post Plaza in Roswell, NM. It was determined that at the time of the inspection that the Respondent had neither developed a Storm Water Pollution Plan (SWPPP) nor applied for permit coverage as required by the Clean Water Act. Because the Respondent met the criteria of the Expedited Settlement Offer (ESO), that enforcement action was drafted. Contact: Diana McDonald, 6EN-WC, (214) 665-7495
Defendants (1)
- Julian P. Barry Gen.Contr., LP (NMU001409) (SB)Named in complaintNamed in settlement
Facilities (1)
OLD POST PLAZA
1705 NORTH MAIN STREET, ROSWELL, NM, 88202
Registry ID: 110017695760
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Julian P. Barry General Contractor, LP (NMU001409)entered 2004-05-27
Primary law: CWA
Timeline (3 milestones)
- 2004-05-20Enforcement Action Data Entered
- 2004-05-27Final Order Issued
- 2004-09-15Enforcement Action Closed
Case metadata
- EPA activity ID
- 119763
- Case number
- 06-2004-2134
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations