EPA v. WW Construction, Inc. (NMR15D320)
Unilateral Administrative Order Without Adjudication
Case summary
Violations: 1. Respondent failed to describe all pollution control measures that will be implemented to control pollutants in storm water discharges in the Storm Water Pollution Prevention Plan (SWPPP). 2. Respondent failed to describe interim and permanent stabilization practices in the SWPPP. 3. Respondent failed to ensure implementation of pollution prevention measures for non-storm water discharges. 4. Respondent failed to post the permit notice and a copy of the completed Notice of Intent (NOI) at the main entrance of the construction site. 5. Respondent failed to sign and certify the SWPPP. 6. Respondent failed to properly select, install, and maintain control measures.
Defendants (1)
- WW Construction, Inc.Named in complaintNamed in settlement
Facilities (1)
NM 48 HWY. RECONSTRUCTION
NM 48 & NM37 INTERSECTION, ALTO, NM, 88312
Registry ID: 110017345229
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
WW Construction, Inc. (NMR15D320)entered 2004-04-08
Primary law: CWA
Timeline (3 milestones)
- 2004-04-08Final Order Issued
- 2004-04-13Enforcement Action Data Entered
- 2004-06-11Enforcement Action Closed
Case metadata
- EPA activity ID
- 116788
- Case number
- 06-2004-2077
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2004-2077 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.