EPA v. Lee Lewis Construction, Inc. (TXR158416)
Unilateral Administrative Order Without Adjudication
Case summary
Lee Lewis Construction, Inc., Fine Arts Complex (TXR158416): A storm water compliance inspection wasa conducted by EPA on February 3, 2004, at the construction site of the Fine Arts Complex. Lee Lewis Construction, Inc., had applied for permit coverage under the Storm Water Construction General Permit and been assigned permit number TXR158416. It was determined that while Lee Lewis had permit coverage, its Storm Water Pollution Prevention Plan (SWPPP) was deficient in several areas and was not in compliance with the requirements of the permit. Lee Lewis, however, qualified for the Expedited Settlement Offer (ESO, which has been drafted. Contact: Diana McDonald (6EN-WC), 214-665-7495
Defendants (1)
- Lee Lewis Construction, Inc. (TXR158416) (SB)Named in complaintNamed in settlement
Facilities (1)
WTAMU FINE ARTS COMPLEX
3RD AVENUE & WISDOM ROAD, CANYON, TX, 79016
Registry ID: 110016753725
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Lee Lewis Construction, Inc. (TXR158416)entered 2004-03-05
Primary law: CWA
Timeline (3 milestones)
- 2004-02-24Enforcement Action Data Entered
- 2004-03-05Final Order Issued
- 2004-07-13Enforcement Action Closed
Case metadata
- EPA activity ID
- 111968
- Case number
- 06-2004-1983
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations