Skip to main content
06-2004-1906Administrative - FormalClosedFY 2004· Region 06

EPA v. Kere, Inc. / Starbuck Coffee Shop (TXU010286)

Unilateral Administrative Order Without Adjudication

Case summary

A storm water compliance inspection was conducted April 17, 2003, by EPA at the construction site of a Starbucks Coffee shop within the Red Rock Shopping Center in El Paso, TX. At the time of the inspection, it was determined that Kere, Inc., had not applied for permit coverage under either the EPA�s Construction General Permit or the Texas Construction General Permit. Although there was a silt fence surrounding the site, it was improperly installed, resulting in silt escaping the site. An administrative order was drafted to address the violations.

Defendants (1)

  • Kere, Inc. (TXU010286)Named in complaintNamed in settlement

Facilities (1)

  • STARBUCKS COFFEE

    RED ROCK SHOPPING CENTER, EL PASO, TX, 79912

    Registry ID: 110014407588

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Kere, Inc. (TXU010286)entered 2003-12-18

    Primary law: CWA

Timeline (3 milestones)

  • 2003-11-14Enforcement Action Data Entered
  • 2003-12-18Final Order Issued
  • 2004-02-11Enforcement Action Closed

Case metadata

EPA activity ID
108345
Case number
06-2004-1906
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2004-1906 . Bulk data: ICIS-FEC download summary.