EPA v. Frank Dale Construction, Ltd. (TXU010331)
Final Order With Penalty
Case summary
An inspection for storm water compliance was conducted by EPA on November 15, 2003. During the inspection it was noted that the Storm Water Pollution Prevention Plan (SWPPP) was inadequate in that it did not identify all potential sources of pollution, did not identify all operators, the site description was incomplete, there was no sequence of events, there was no copy of the permit6, the SWPPP was not signed and certified, there was no construction sign posted, and control measures were not properly maintained. It was determined that this facility did qualify for the Expedited Settlement Offcer and was issued an order to come into compliance. A Consent Agreement and Final Order for penalties was also issued and is awaiting the 30-day public notice period and final signatures
Defendants (1)
- Frank Dale Construction, Ltd. (TXU010331) (SB)Named in complaintNamed in settlement
Facilities (1)
ARLINGTON PRESBYTERIAN CHURCH
SANCTUARY, ARLINGTON, TX, 76013
Registry ID: 110015715546
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Frank Dale Construction, Ltd. (TXU010331)entered 2004-02-26
Primary law: CWA
Federal penalty: $3,150
Timeline (5 milestones)
- 2004-01-07Enforcement Action Data Entered
- 2004-02-26Complaint Filed/Proposed Order
- 2004-02-26Final Order Issued
- 2009-07-01Enforcement Action Closed
- 2009-07-01NPDES Closed
Case metadata
- EPA activity ID
- 109912
- Case number
- 06-2004-1786
- Lead agency
- EPA
- Branch
- 6EN-W
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2004-1786 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.