EPA v. Sparling Construction Co., Inc. (NMR10C631)

Unilateral Administrative Order Without Adjudication

Case summary

A storm water compliance inspection was conducted April 1, 2003, at the Quemazon Communities in Los Alamos, NM. Sparling Construction Co., Inc., was found in non-compliance due to there being no storm water pollution prevention plan (SWPPP) being available for review and there was no Notice of Intent (NOI) posted as required by the permit. An administrative order was drafted to address these violations.

Defendants (1)

  • Sparling Construction Co., Inc. (NMR10C631)Named in complaintNamed in settlement

Facilities (1)

  • SPARLING CONSTRUCTION CO. INC. / QUEMAZON COMMUNITIES (NMR10C631)

    8900 WASHINGTON NE, SUITE C, ALBUQUERQUE, NM, 87199

    Registry ID: 110015768070

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Sparling Construction Co., Inc.entered 2003-12-05

    Primary law: CWA

Timeline (3 milestones)

  • 2003-10-30Enforcement Action Data Entered
  • 2003-12-05Final Order Issued
  • 2009-07-01Enforcement Action Closed

Case metadata

EPA activity ID
107667
Case number
06-2004-1781
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2004-1781 . Bulk data: ICIS-FEC download summary.