EPA v. Afco Steel - South Plant
Final Order With Penalty
Case summary
1. Plan not certified by a professional engineer. 2. No management approval of plan. 3. No designated person responsible for spill prevention. 4. Spill prevention briefings are not scheduled and conducted periodically.
Defendants (1)
- Afco Steel, South PlantNamed in complaintNamed in settlement
Facilities (1)
AFCO STEEL,SOUTH PLANT
1500 EAST 22ND STREET, LITTLE ROCK, AR, 72202
Registry ID: 110001710168
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
Afco Steel, South Plantentered 2003-04-21
Primary law: CWA
Federal penalty: $700
Timeline (4 milestones)
- 2003-03-03Complaint Filed/Proposed Order
- 2003-03-25Enforcement Action Data Entered
- 2003-04-21Final Order Issued
- 2003-04-29Enforcement Action Closed
Case metadata
- EPA activity ID
- 92972
- Case number
- 06-2003-4306
- Lead agency
- EPA
- Branch
- 6SF-R
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2003-4306 . Bulk data: ICIS-FEC download summary.