EPA v. Grand Resources, Inc.
Final Order With Penalty
Case summary
*Plan not certified by a professional engineer *Written procedures and a record of inspections are not made part of the plan. *Visual tank inspections are not conducted periodically by appropriate personnel and/or inspections do not include tank foundation and supports. *Above ground valves and pipelines are not examined periodically on a scheduled basis for general condition (includes items, such as: flange joints, valve glands 2nd bodies, drip pans, pipeline supports, bleeder and guage valves, polish rods/stuffing box.
Defendants (1)
- Grand Resources, Inc.Named in complaintNamed in settlement
Facilities (1)
GRAND RESOURCES, INC. BLAZER LEASE FACILITY
2448 EAST 81TH STREET, NO. 4040, OSAGE COUNTY, OK, 74137
Registry ID: 110010778300
Statutes cited
- CWA 311J — SPCC and/or Federal Response Plan Violations
Enforcement conclusions (1)
Grand Resourcesentered 2003-01-27
Primary law: CWA
Federal penalty: $950
Timeline (4 milestones)
- 2002-12-02Complaint Filed/Proposed Order
- 2003-01-27Enforcement Action Closed
- 2003-01-27Final Order Issued
- 2003-01-30Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 90908
- Case number
- 06-2003-4301
- Lead agency
- EPA
- Branch
- 6SF-R
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- SPCC and/or Federal Response Plan Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2003-4301 . Bulk data: ICIS-FEC download summary.