Skip to main content
06-2003-1947Administrative - FormalClosedFY 2003· Region 06

EPA v. Contour Energy E&P, Inc. (GMG290255)

Unilateral Administrative Order Without Adjudication

Case summary

Respondent failed to have Clean Water Act NPDES permit coverage for the following facilities from upon purchase of assets from December 10, 1997, until April 16, 2002, for the following Gulf of Mexico offshore platforms: Vermilion 217, Vermilion 218, Matagorda Island 603, Matagorda Island 620, Brazos 338-L, and Brazos Block 444-S. Respondent failed to have NPDES permit coverage for the following facilities starting December 10, 1997, and remaining unpermitted as of the date of this Order for the following facilities: Matagorda Island 619, Brazos 339, Brazos 337-L, Brazos 368, Brazos 340-L. Respondent is Orderd to obtain NPDES permit coverage for all offshore facilities in the Gulf of Mexico.

Defendants (1)

  • Contour Energy E&P, Inc. (GMG290255)Named in complaintNamed in settlement

Facilities (1)

  • CONTOUR ENERGY CO. - GULF OF MEXICO

    1001 MCKINNEY, STE 900, HOUSTON, TX, 77002

    Registry ID: 110013724158

Statutes cited

  • CWA 301/402NPDES Permit Violations
  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Contour Energy E&P, Inc. (GMG290255)entered 2003-05-14

    Primary law: CWA

Timeline (3 milestones)

  • 2003-04-29Enforcement Action Data Entered
  • 2003-05-14Final Order Issued
  • 2003-07-14Enforcement Action Closed

Case metadata

EPA activity ID
95731
Case number
06-2003-1947
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations