Skip to main content
06-2003-1894Administrative - FormalClosedFY 2003· Region 06

EPA v. Harlingen, City of

Unilateral Administrative Order Without Adjudication

Case summary

The city of Harlingen, a municpality. Owns and operates a wastewater treatment plant and was issued a TPDES Permit authorizing its discharges. The city of Harlingen has exceeded its permitted limits for CBOD, COD, TSS, and Color and the EPA has issued an Administrative Order to the city asking addressing the violations and asking for information regarding bringing the facility back into compliance.

Defendants (1)

  • Mr. Cloice Whitley, General ManagerNamed in complaintNamed in settlement

Facilities (1)

  • CITY OF HARLINGEN WATERWORKS SYSTEM WWTP

    504 54TH ST, HARLINGEN, TX, 78550

    Registry ID: 110039693524

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • Harlingen, City ofentered 2003-03-25

    Primary law: CWA

Timeline (5 milestones)

  • 2003-03-20Enforcement Action Data Entered
  • 2003-03-25Final Order Issued
  • 2009-10-13Enforcement Action Closed
  • 2009-10-13Compliance Achieved
  • 2009-10-13NPDES Closed

Case metadata

EPA activity ID
92710
Case number
06-2003-1894
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2003-1894 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.