EPA v. San Juan Coal Company
Unilateral Administrative Order Without Adjudication
Case summary
Respondent had an upset condition due to a significant rainfall in Sept. 2002, resulting in a discharge with some effluent violations. Facility is a coal company and normally they have no discharge. Respondent also failed to submit a construction schedule report on time and it was about 8 months late. EPA is ordering facility to make changes to assure any future discharges meet the effluent limits and that Respondent turns in environmental reports on time.
Defendants (1)
- San Juan Coal CompanyNamed in complaintNamed in settlement
Facilities (2)
SAN JUAN COAL COMPANY-SAN JUAN
SAN JUAN, NM
Registry ID: 110000744035
SAN JUAN COAL COMPANY-SAN JUAN
SAN JUAN, NM
Registry ID: 110000744035
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
San Juan Coal Companyentered 2003-02-14
Primary law: CWA
Timeline (3 milestones)
- 2003-02-05Enforcement Action Data Entered
- 2003-02-14Final Order Issued
- 2009-07-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 91062
- Case number
- 06-2003-1836
- Lead agency
- EPA
- Branch
- 6RC-E
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2003-1836 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.