06-2003-1826Administrative - FormalClosedFY 2003· Region 06

EPA v. Choice Homes, Inc. (TXR10TA95)

Unilateral Administrative Order Without Adjudication

Case summary

Violations: 1. Inspection reports did not include unstabilized disturbed areas, locations where vehicles enter or exit, or material storage areas exposed to precipitation. 2. The inspection reports did not indicate if corrections are made within seven days. 3. Permit and SWPPP information were in an unmarked mailbox behind a Choice Homes sign at the entry of the development. 4. There was a poorly maintained concrete truck washout area, and the silt fencing was not properly buried along the bottom edge. 5. Storm drain protector was pulled back to allow unimpeded flow of sediment. 6. Controls were poorly maintained which allowed for offsite tracking. 7. Soil, construction debris and litter was found in the streets.

Defendants (1)

  • Choice Homes, Inc.Named in complaintNamed in settlement

Facilities (1)

  • EAGLE'S PEAK NEST DEVELOPMENT

    FM 16 WEST, LINDALE, TX, 75771

    Registry ID: 110013402317

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • Choice Homes, Inc.entered 2003-02-07

    Primary law: CWA

Timeline (3 milestones)

  • 2003-01-31Enforcement Action Data Entered
  • 2003-02-07Final Order Issued
  • 2009-07-01Enforcement Action Closed

Case metadata

EPA activity ID
90954
Case number
06-2003-1826
Lead agency
EPA
Branch
6EN-W
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations