VIOLATION: 1) Unauthorized discharges noted during EPA inspection; and 2) Onshore oil and gas producers are required to contail or dispose of produced waters in a manner protective of the environment, including underground injection. **RELIEF SOUGHT: 1) Upon receipt of this Order, the Respondent immediately shall cease all unpermitted discharges of pollutants from the facility; 2) Within thirty days, the Respondent shall take the listed corrective action necessary to eliminate and prevent recurrence of the violations; and 3) Within thirty days, Respondent shall schedule and meet with and EPA Field Inspector to confirm that the listed tasks have been completed
Defendants (1)
- CRM ENERGYNamed in complaintNamed in settlement
Facilities (2)
NW-23-23-11
NW/4, SEC. 23, T 23N, R 11E, AVANT, OK, 74001
Registry ID: 110013704562
NE-31-23-11
NE/4, SEC. 31, T 23N, R 11E, AVANT, OK, 74001
Registry ID: 110017749506
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
CRM Energyentered 2002-11-04
Primary law: CWA
Timeline (3 milestones)
- 2002-11-04Final Order Issued
- 2002-12-11Enforcement Action Data Entered
- 2003-09-16Enforcement Action Closed
Case metadata
- EPA activity ID
- 89386
- Case number
- 06-2003-1760
- Lead agency
- EPA
- Branch
- 6RC-E
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit