06-2002-1946Administrative - FormalClosedFY 2002· Region 06

EPA v. EL Paso Production Company (GMG290124)

Unilateral Administrative Order Without Adjudication

Case summary

'VIOLATION: Failure to obtain NPDES permit coverage for discharges of pollutants to waters of the United States. **RELIEF: 1) Within thirty days, the Respondent shall take corrective action for all violations and submit a written report detailing the specific actions taken; 2) Respondent shall provide information in a report about unpermitted facilities; 3) If complete correction of violations is not possible within thirty days, submit a comprehensive plan to do so; 4) If Respondent did have permit coverage, submit a report with copy of NOI application and proof of delivery; and 5) Within forty-five days, arrange a Show Cause meeting with EPA.

Defendants (1)

  • EL Paso Production Company, a Delaware corporationNamed in complaintNamed in settlement

Facilities (1)

  • EL PASO PRODUCTION COMPANY, A DELAWARE CORPORATON (GMG290015)

    1001 LOUISIANA STREET, HOUSTON, TX, 77002

    Registry ID: 110005117480

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • EL Paso Production Company, a Delaware corporationentered 2002-09-18

    Primary law: CWA

Timeline (3 milestones)

  • 2002-09-18Final Order Issued
  • 2002-09-27Enforcement Action Data Entered
  • 2009-07-01Enforcement Action Closed

Case metadata

EPA activity ID
86088
Case number
06-2002-1946
Lead agency
EPA
Branch
6RC-E
EPA region
06
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit