EPA v. Weldon Buddy Alders, an individual
Unilateral Administrative Order Without Adjudication
Case summary
'VIOLATION: 1) Respondent did not make timely application for permit coverage for conducted activities; 2) No development of a Pollution Prevention Plan; and 3) Respondent has no best management practices (BMPs) at the site. **RELIEF: 1) Within thirty days, Respondent shall make complete and correct application for permit and submit copy of application and coverage; 2) Within thirty days, take corrective action to correct deficiences and eliminate and prevent recurrence of violations; 3) Within thirty days, submit written report of specific actions taken; and 4) If complete correction of violations is not possible within thirty days, submit comprehensive plan to do so.
Defendants (1)
- Weldon Buddy AldersNamed in complaintNamed in settlement
Facilities (1)
WELDON BUDDY ALDERS, AN INDIVIDUAL
ALDERS COMPANY, P.O. BOX 10, DAYTON, TX, 77535
Registry ID: 110013690942
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Weldon Buddy Aldersentered 2002-08-30
Primary law: CWA
Timeline (4 milestones)
- 2002-08-30Complaint Filed/Proposed Order
- 2002-08-30Final Order Issued
- 2002-09-04Enforcement Action Data Entered
- 2009-07-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 85279
- Case number
- 06-2002-1905
- Lead agency
- EPA
- Branch
- 6RC-E
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2002-1905 . Bulk data: ICIS-FEC download summary.