EPA v. Bosque River Chase, L.T.D.and H & B Contractors
Final Order With Penalty
Case summary
'**VIOLATIONS: 1) Inspections were not documented in the SWPPPfrom May 7, 2001 to July 14, 2001; 2) One construction entrance to the site was unstabilized; and 3) The silt fence around the 25 partially or completed storm sewer inlets was either poorly installed or poorly maintained. **PROPOSED PENALTY: $27,500.00. '
Defendants (2)
- Bosque River Chase, L.T.D.Named in complaintNamed in settlement
- H & B ContractorsNamed in complaintNamed in settlement
Facilities (1)
VILLAGE AT TWIN RIVERS
HIGHWAY 84 AND TWIN RIVERS BOULEVARD, WACO, TX, 76712
Registry ID: 110010650063
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
Bosque River Chase, L.T.D. and H & B Contractorsentered 2002-12-12
Primary law: CWA
Federal penalty: $9,000
Timeline (4 milestones)
- 2002-09-19Complaint Filed/Proposed Order
- 2002-10-09Enforcement Action Data Entered
- 2002-12-12Final Order Issued
- 2003-09-16Enforcement Action Closed
Case metadata
- EPA activity ID
- 86690
- Case number
- 06-2002-1878
- Lead agency
- EPA
- Branch
- 6RC-E
- EPA region
- 06
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations