EPA v. OPELOUSAS, CITY OF, A LOUISIANA MUNICIPALITY
Unilateral Administrative Order Without Adjudication
Case summary
'Violation: Violating the permit requirements. Relief Sought: a) provide a comprehensive construction progress summary for phases I and II rehabilitation activities; b) report on the corrective actions taken; and c) submit a comprehensive plan for corrective action if not possible to correct the violations in 30 days.'
Defendants (1)
- OPELOUSAS, CITY OFNamed in settlement
Facilities (1)
OPELOUSAS CITY OF
CYPRESS ST GROLEE ST, OPELOUSAS, LA, 70570
Registry ID: 110002046090
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
OPELOUSAS, CITY OFentered 2002-06-06
Primary law: CWA
Timeline (4 milestones)
- 2002-06-06Complaint Filed/Proposed Order
- 2002-06-06Final Order Issued
- 2002-06-14Enforcement Action Data Entered
- 2009-07-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 41998
- Case number
- 06-2002-1829
- Lead agency
- EPA
- HQ division
- WAT
- Branch
- 6RC-E
- EPA region
- 06
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit