EPA v. MARK WHEELER HOMES, INC. AND HOMES BY KEN WHEELER, JR., INC.
Unilateral Administrative Order Without Adjudication
Case summary
'Violation: no permit. Relief Sought: a) obtain npdes permit; b) take corrective actions: c) report on corrective actions; and d) submit a comprehensive plan for corrective action if not able to correct the violation in 30 days.'
Defendants (2)
- HOMES BY KEN WHEELER, JR., INC.Named in settlement
- MARK WHEELER HOMES, INC.Named in settlement
Facilities (1)
COLLEY CONSTRUCTION
3311 WOODS BLVD., TYLER, TX, 75707
Registry ID: 110010130946
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
MARK WHEELER HOMES, INC. AND HOME BY KEN WHEELER,entered 2002-06-06
Primary law: CWA
Timeline (4 milestones)
- 2002-06-06Complaint Filed/Proposed Order
- 2002-06-06Final Order Issued
- 2002-06-14Enforcement Action Data Entered
- 2009-07-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 41994
- Case number
- 06-2002-1825
- Lead agency
- EPA
- HQ division
- WAT
- Branch
- 6RC-E
- EPA region
- 06
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2002-1825 . Bulk data: ICIS-FEC download summary.