06-2000-0846Administrative - FormalFinal Order IssuedFY 2000· Region 06

EPA v. DEL RIO, CITY OF EAST WATER PLANT

Final Order With Penalty

Penalty assessed

$2,500

Case summary

1. SECTION 113(D) OF THE CLEAN AIR ACT ( CAA ), 42 U.S.C. SECTION 7413(D). 2. CITY OF DEL RIO EAST WATER PLANT IN THE SAN FELIPE GOLF COURSE DEL RIO, VAL VERDE COUNTY, TEXAS 78841 3. RESPONDENT WAS IN VIOLATION OF SECTION 112(R)(7) OF THE CAA BY FAILING TO DEVELOP AND SUBMIT A RISK MANAGEMENT PLAN (RMP) TO EPA BY THE REQUIRED JUN. 21, 1999 DEADLINE. 4. RELIEF SOUGHT PURSUANT TO SECTION 113(D), EPA ASSESSED THE RESPONDENT A CIVIL PENALTY OF $2,500 FOR THE VIOLA- TION CITED. PAYMENT OF THE PENALTY AND THE RISK MANAGE- MENT PLAN ARE DUE TO EPA WITHIN 45 DAYS OF THE RESPONDENT SIGNING THE SETTLEMENT AGREEMENT.

Defendants (1)

  • DEL RIO, CITY OFNamed in complaintNamed in settlement

Facilities (1)

  • DEL RIO CITY OF, EAST WATER PLT

    IN THE SAN FELIPE GOLF COURSE, DEL RIO, TX, 78841

    Registry ID: 110010722398

Statutes cited

  • CAA 112RGeneral Duty/Accidental Release

Enforcement conclusions (1)

  • DEL RIO, CITY OF EAST WATER PLANTentered 2000-09-01

    Primary law: CAA

    Federal penalty: $2,500

Timeline (3 milestones)

  • 2000-06-21Complaint Filed/Proposed Order
  • 2000-06-26Enforcement Action Data Entered
  • 2000-09-01Final Order Issued

Case metadata

EPA activity ID
40462
Case number
06-2000-0846
Lead agency
EPA
HQ division
AIR
Branch
6SF-R
EPA region
06
Multimedia
No
Voluntary self-disclosure
No
Primary statute
General Duty/Accidental Release

Sourced verbatim from EPA ECHO Enforcement Case Report for case 06-2000-0846 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.